Pre-Filing Decisions Often Cause Commercial Permit Delays, Architect Says

By Burstable Editorial Team
Mike Marden of WDS Architecture explains that commercial construction delays often stem from pre-filing approaches, such as relying on generic city advice and sequential project sequencing, and advocates for integrated design-build to compress timelines.
Pre-Filing Decisions Often Cause Commercial Permit Delays, Architect Says

Municipal permitting remains the most cited source of commercial construction delays, but Mike Marden, a registered architect and licensed general contractor at WDS Architecture in Phoenix, argues that the most damaging delays occur before a single document is filed. Marden points to two critical pre-filing pitfalls: treating informal city conversations as authoritative guidance and following a sequential project model that inherently extends timelines.

The first issue, according to Marden, is the 'scripted answer problem.' Clients often call the city, describe their project in general terms, and receive generic responses about typical timelines and required documentation. These conversations are rarely project-specific, and the checklists provided may include irrelevant requirements while omitting critical ones. 'They often say, we already spoke with someone at the city. They said we just turn in this form and this is roughly the time,' Marden says. 'First of all, that's not a documented conversation. There is no log number or record. None of that's official. And everything on the checklist might not even apply.' Clients planning around such informal advice risk discovering discrepancies only after entering the review process, costing months.

Beyond information gaps, Marden highlights the structural delay inherent in the conventional sequential model: complete design, submit for permits, wait for approval, then start construction. This approach treats permitting as a gate, during which no construction progress occurs. The client's lease clock runs, contractors wait, and trade partners are held unavailable. 'We see this every time we are “Architect only” on a project,' Marden says. He also notes that the gap between design completion and construction start is often widened by contractor selection and mobilization. Clients who finish drawings before searching for a contractor add weeks or months to their timeline before permits are even submitted. 'Did you think about the gap where you're bidding and trying to find a contractor, meanwhile, permits are ready and you've signed the lease?' Marden asks.

Firms that consistently meet permit timelines do so by compressing the process, not by speeding through it. They engage the city early with preliminary questions, understand the specific requirements of inspectors in their jurisdictions, and begin non-permitted construction activities while review is underway. This approach is possible when the architect and contractor are integrated from the start. Marden explains that at WDS Commercial, 'We can start building the project as we're turning in for a permit. We're the contractor, already contracted with the Owner, and have spent months participating in the design. If we are questioned or told to turn in drawings, well, we have already done that because we are also the Architect! We can go right up to first inspection with our work, gaining a month versus waiting on bid results, contracts, permits, and mobilization, losing a month or two.'

WDS Architecture's dual credentials as both an architecture firm and general contractor enable this parallel approach. By mobilizing for construction activities outside the permit scope—such as staging, layout, scoping, testing, demo, subcontracting, and ordering materials—during review, they compress timelines without cutting compliance corners. The firm also leverages ongoing relationships with local jurisdictions to provide realistic project assessments. 'Over here, where we do this every day, we know what really needs to go in, how long it's really going to take,' Marden says.

Marden advises clients to engage on permitting strategy during site selection, before signing a lease. A location that appears inexpensive may carry hidden permitting complexity, while a pricier clean site could deliver a faster opening. 'It's like building a project twice, when dealing with existing conditions, removing what is there so that new material can be installed to meet code,' he says. For Phoenix business owners planning commercial build-outs, the implication is clear: expected permit timelines often understate reality, and the gap originates in pre-filing decisions, not city processing speed.

Burstable Editorial Team

Burstable Editorial Team

@burstable

Burstable News™ is a hosted solution designed to help businesses build an audience and enhance their AIO and SEO press release strategies by automatically providing fresh, unique, and brand-aligned business news content. It eliminates the overhead of engineering, maintenance, and content creation, offering an easy, no-developer-needed implementation that works on any website. The service focuses on boosting site authority with vertically-aligned stories that are guaranteed unique and compliant with Google's E-E-A-T guidelines to keep your site dynamic and engaging.